Brenner Base Tunnel boring completed

TBM Olga has completed the east main tube of the Brenner Base Tunnel. Connecting galleries and shafts remain outstanding, and entry into service has slipped to 2034 under a revised programme and budget.

Brenner Base Tunnel boring completed
Workers standing next to the cutting head of the ‘Olga’ tunnel-boring machine following the breakthrough of the eastern tube of the Brenner Base Tunnel. © BTT SE.

Miguel Bustos | 25-11-2026.

Olga, the last tunnel boring machine (TBM) still working on the Brenner Base Tunnel, reached its destination on the Austrian side on 24 November. Her arrival marks the end of mechanised excavation on the 55 km underground link between Austria and Italy.

Olga bored some 7.6 km of the east main tube towards Innsbruck, within the H53 Pfons–Brenner construction lot. She began work on 18 September 2024 alongside her sister machine Wilma.

WhatsApp

Wilma completed her 7.45 km drive in the west main tube on 25 August. With yesterday’s breakthrough, the first continuous railway tunnel between Innsbruck and Fortezza (Franzensfeste) has been bored.

Nine TBMs, eight from Herrenknecht

Olga’s arrival ends the work of the nine TBMs deployed on the project, eight of which were supplied by German manufacturer Herrenknecht. However, the connecting galleries and shafts remain to be built, as does the installation of the railway superstructure. This work is expected to take eight years.

The milestone follows the July connection of the Austrian and Italian sections of both main tubes. That link was built using conventional (drill-and-blast) excavation and joined the two countries beneath the Alps. Meanwhile, Olga and Wilma continued northwards towards the neighbouring Sill Gorge – Pfons lot.

Revised programme and cost

On 20 October, project promoter BBT SE announced a new programme and cost forecast. Entry into service moves from 2032 to 2034, while the total estimated cost rises from €10.5bn to €11.7bn.

BBT SE attributes the changes to an update of the railway system’s design. Among other measures, the exploratory tunnel is to be adapted for conversion into a service tunnel. The new estimate also covers additional infrastructure and a longer construction period.

A key link on the Scandinavian-Mediterranean Corridor

The tunnel will link Innsbruck with Fortezza. Together with the existing Innsbruck railway bypass, it will form a 64 km underground connection. It is a key element of the Scandinavian-Mediterranean Corridor of the TEN-T network and is intended to increase capacity for passenger and freight trains crossing the Alps.