Andalusia’s minister for transport and mobility, Mario Muñoz-Atanet, has reiterated that the Jaén tram will become a reality in December if the tests proceed successfully. The blank-running phase will begin on Monday 30 November and will simulate commercial service using real timetables, frequencies and stops, although without passengers.
If no major incidents arise during this stage, Andalusian President Juanma Moreno has confirmed that the tram could begin running over the Christmas period. Jaén mayor Julio Millán has placed the expected opening date at 20 December, after estimating that the blank-running tests will last between two and three weeks.
Final testing from 30 November
Blank-running tests represent the final step before the system enters service. During this period, the tramcars will operate on a schedule equivalent to regular service, aiming to validate the full operating regime: journey times, frequency regulation, station stops, and coordination with signalling and safety systems.
The outcome of these tests will be decisive in setting the definitive opening date. The regional administration has stressed that commissioning will depend on the tests proceeding without incidents requiring technical or organisational corrections.
Years of delays and unfulfilled promises
The December start of service follows a long history of delays. The Jaén tram was inaugurated in May 2011 and briefly operated a free trial service for just over two weeks before being suspended amid a dispute with the private urban bus operator, which alleged unfair competition, and the absence of a funding formula for commercial operation.
Since then, the infrastructure has remained out of service for more than a decade and a half. The Andalusian government announced its launch on several occasions for 2022, 2023, 2024 and 2025, deadlines it did not meet, fuelling criticism from the city council and local political groups.
The revival of the project, driven forward since 2019, has required upgrading infrastructure built more than 15 years ago, commissioning the Alstom Citadis vehicles, and resolving the operation and maintenance contracts. In 2025, the Andalusian government acknowledged that operator testing could not begin until early 2026, despite earlier expectations that the service would be running by the end of 2025.
Procuring the operating contract has been one of the main bottlenecks. The award was delayed after several bidders were excluded for formal errors, while the infrastructure required adaptation to current safety, operations, and accessibility standards. Finally, in April this year, the consortium formed by Grupo Ruiz and Barraqueiro won the operating contract.
Meeting between Andalusia and city council
The Andalusian government and Jaén city council will meet on 1 December to discuss the tram’s commissioning. The meeting will review coordination between the two administrations at a particularly sensitive time, given the impact of the works and changes to urban traffic.
Millán had previously met traders in the city centre, who expressed concern about the economic losses they attribute to changes in traffic circulation. The mayor has defended the measures, saying that they have been explained to traders with technical data, both those already adopted and those planned, and has maintained that alternative access routes and park-and-ride facilities are available for travel to the centre.
Traffic and reserved track
The mayor has ruled out allowing use of the tram’s reserved track, one of the measures requested by his governing coalition partner, Jaén Merece Más. Millán has argued that the track is linked to a traffic-signal system connected to sensors in the rails, and that other traffic using it could disrupt the sensors’ operation.
The mayor has defended the planning as responding to traffic needs and has expressed confidence that traffic conditions will normalise in the coming days. The commissioning of the Jaén tram therefore represents a combined test of technical reliability and of the city’s ability to manage traffic in the city centre.