Hitachi challenges Renfe’s award of 30 high-speed trains

First delays emerge in the manufacture of the 30 high-speed trains awarded by Renfe to Siemens. Hitachi, the German manufacturer’s rival in the tender, has challenged the process. Contract signature could be delayed by months.

Hitachi challenges Renfe’s award of 30 high-speed trains
Hitachi logo on the former headquarters of Thales España in Madrid. © HITACHI RAIL.

Miguel Bustos | 28-11-2026.

Hitachi Rail has lodged a challenge before Spain’s Central Administrative Court for Contractual Appeals (TACRC) against Renfe’s award to Siemens Mobility for 30 new high-speed trains, elEconomista.es reported yesterday. The appeal was filed before the contract was formalised, suspending its signature until the court rules.

What Hitachi is contesting

The Italian-Japanese manufacturer argues that its ETR1000 offered a more competitive price and shorter delivery times. According to the outlet’s sources, it also disputes the capacity and energy-consumption assumptions Renfe used to calculate lifetime savings. It further questions whether Siemens can develop and homologate, within 37 months, a platform that has not yet entered commercial service.

Renfe selected the Velaro Novo, Siemens’ latest evolution of its high-speed train family. However, only one intermediate car has been built so far to homologate the platform in Germany. Although it has been sold to Vietnam, and the US version, American Pioneer, to Brightline, manufacturing has not yet begun; it is therefore more of a project than a reality.

The ETR1000, in its first generation (the 400 series in Italy), is already homologated in Spain, where Iryo operates it, and it also runs in France and Italy. It is close to being homologated in Austria and Germany following modifications to some units, including the electromagnetic brake. The second generation (the 410 series in Italy) has only been homologated in its home market.

In Spain, it would require additional homologation, although this would in any case be shorter than that required for an entirely new train.

The order in numbers

Siemens won the tender at €1,218.1 million excluding VAT, against a maximum price of €1,362 million. That equates to around €40.6 million per train before VAT. With VAT, the total rises to €1,473.9 million, or around €49.13 million per unit. The order includes an option for ten additional trains.

Renfe stipulated that the first five units must be delivered before month 40, with all 30 delivered within 62 months, compared with the 78 months initially set out in the tender documents. The trains will be seven-car, 200 m formations with 520 seats on a single deck. Hitachi’s proposal offered 461 seats.

The appeal will delay delivery

Filing an appeal against the award automatically suspends the procedure, meaning Renfe cannot formalise the contract until a ruling is issued. The TACRC must decide, within five working days, on precautionary measures and whether the suspension should remain in place.

Based on previous appeals, a reasonable estimate is that contract formalisation could be delayed by between five weeks and two and a half months. The actual timeframe will depend on when the appeal was filed and the case’s complexity.

One reference case in which an appeal was not decisive involved several bidder claims against Renfe awards. One of them, concerning cleaning services, ended in rejection and the lifting of the suspension. The TACRC reviews only material errors, arbitrariness, or a lack of reasoning, not technical discretion in the evaluation. If it rejects the appeal, therefore, the delay would be limited to the procedural process.

A different scenario occurred in Belgium. There, the Council of State halted SNCB’s contract with CAF in April 2025 over a lack of transparency in awarding scores. Following further appeals by Alstom, the process was not cleared until September, almost eight months later. That is a precedent involving a different court and legal system. The same happened in Portugal with the formalisation of the contract to purchase 117 regional trains from Alstom. The award was made in November 2023, but the contract could not be formalised until October 2025 because CAF and Stadler filed challenges.

The acquisition responds to the need to replace the 23 Class 100 units, which have remained in service since 1992. The public operator also seeks to expand its fleet in order to offer more services. Although not officially confirmed, the option for ten additional trains could be linked to Renfe’s plans in France.